-> set up a robust back up system (one weekend)
– due date: October 17th 2010
– dependency: need to set up my home network, have all equipment
-> second pass of animation (one month)
– due date: November 14th 2010
– dependency: need to show another animator and get feedback
-> get a GUI artist involved
– due date: November 28th
– dependency: need to show 2nd anim pass to sell idea to them
-> get a sound designer on board
– due date: November 28th (need to show 2nd anim pass)
– dependency: need to show 2nd anim pass to sell idea to them
-> finalise environment models and shader
– due date: two weeks after anim pass 2 ~ 5th December 10
– dependency: want to get 2nd pass of anim final so I can focus on this
-> finalise shader on Dodo and Mammoth
– due date: 1 week after environment ~ 12th December 10 (can do R&D during lunch hour)
– dependency: want to finalise environment so I can focus on this
-> initial lighting test
– due date: 3 weeks after Dodo/Mammoth shaders ~ 2nd Jan 11 (can do R&D during lunch hour)
– dependency: want to finalise Dodo/Mammoth shaders so I can focus on this
-> finalise lighting
– due date: 4 weeks after initial test, 30th Jan 11 (can do R&D during lunch hour)
– dependency: need all the test data to decide on best set ups and distribute across all shots
-> finalise effects
– due date: 4 weeks after all lighting decisions made 27th Feb 11
– dependency: need to decide about compositing techniques and rendering solutions
-> render sequences
– due date: 3 weeks ~ 20th March 11
– dependency: need everything finished, no changes can be made
-> assemble edit
– due date: 1 week 27th March 11
– dependency: need final frames
-> post processing
– due date: 2 weeks 10th April 11
– dependency: need final edit
-> publish movie to dvd
– due date: 1 week ~ 17th April 11